Define Project Import Settings
Explanation
This activity is used to
define settings for the project data import. Introducing or adjusting
settings for the import ensures that the location of the import file as well as the
way in which the data is imported and any errors notified is known to the user.
Prerequisites
In order to perform this
activity, a project data import document with parameters is required to be
registered in the system.
System Effects
There are no system effects.
Window
Project
Import
Related Window Descriptions
Project Import
Procedure
-
Open the Project Import window and find a project import
header for which you want to define parameters
-
Go to the Document tab.
-
In the Document Number and Document Name
fields, specify an ID and name for the project data import document to which
the import will be done.
-
In the Par Deriv Date field, select a date for the import.
-
In the Select Employee section, select the employees for whom the project data
import will apply.
-
Indicate a period of time for the project data import in the Import Date
From, Import Date To fields.
-
Specify parameters for the project data import in the Import Parameters
section.
-
Save the information.